Shared-Use Path Progress

Shared-Use Path Progress

Around 90% of the shared-use path has been completed as of October 2021. It is not ready for public use yet, but it will be soon! The project team is currently working on removing dead trees in the area to ensure maximum pedestrian and cyclist safety. ...
Ramp H Opening

Ramp H Opening

As of Wednesday, September 8, 2021, Ramp H, which gives I-295 NB access, has been opened up for public traffic use. Ramp H is one of nine ramps that are part of the project’s scope.
Shared-Use Path Progress

Shared-Use Path Progress

Around 75% of the shared-use path has been completed as of August 2021. It is not ready for public use yet, but it will be soon! Most of the retaining walls and the pedestrian hand railings have now been installed. We have also started installing new landscaping and...